JAMMU: Chief Secretary, Atal Dulloo today chaired a comprehensive review meeting to assess the progress of the Tawi Artificial Lake and Riverfront Development Project in Jammu. The review covered key components including riverfront development works, barrage construction, sewerage interception, and protection measures being executed under the Smart City initiative.

The meeting was attended by the Additional Chief Secretary, Jal Shakti Department; Commissioner Secretary, Housing & Urban Development Department (H&UDD); Divisional Commissioner, Jammu; Commissioner Secretary, Law; Commissioner, Jammu Municipal Corporation (JMC); Deputy Commissioner, Jammu; Chief Engineer, PWD/UEED; and other concerned officers.

The Chief Secretary undertook a detailed assessment of both completed and ongoing works, including new initiatives aimed at enhancing the project’s aesthetic appeal and public utility. He also reviewed restoration works necessitated by damages caused during last year’s flash floods. Stressing the importance of timely completion, he directed all concerned departments to ensure that this major city beautification project is dedicated to the public at the earliest, with all requisite amenities in place.

Reviewing the progress of the Tawi Barrage (Artificial Lake), Additional Chief Secretary, Jal Shakti Department, Shaleen Kabra informed that all 31 gates including 11 at Waddi Tawi and 20 at Nikki Tawi have largely been installed, with hydromechanical works nearing completion.

He detailed out that the electrical works, including transformers had seen the progress of around 70% while that of HT/LT panels has witnessed completion status of 60%. Similarly he added that the main distribution panels (80%), and SCADA systems (50%), are at advanced stages. Civil works such as piers, cement concrete blocks, toe walls, gabions, and the control room building (98% complete) are nearing completion, although some components at Nikki Tawi are still in progress.

He further informed that the remaining works required for operationalisation of barrage gates, including embedded components and concreting of service gate grooves, are targeted for completion by the month end.

Commissioner Secretary, H&UDD, Mandeep Kaur informed that Phase-1 (Part A) of the riverfront project has been completed. This phase includes the development of a 2.7 km-long four-level promenade and 2.5 km of interceptor drains, resulting in the reclamation of approximately 440 kanals of land. She added that retaining walls have been constructed 1.5 metres above the highest flood level recorded in 2014 and have withstood recent flood events without any distress, demonstrating the robustness of the design and execution.

Meanwhile, Divisional Commissioner, Jammu, Ramesh Kumar apprised the meeting that construction of a four-lane road on the right bank is progressing steadily. The project includes a 35-metre span RCC bridge over the Ranbir Canal and Distributary-9, with 50% physical and 33% financial progress achieved so far.

He made out that the road will connect Bhagwati Nagar rotary with Bikram Chowk and is expected to significantly ease congestion along the Canal Road–Jewel Chowk corridor. Protection works, drainage, and underground utility provisions are also included in this component, he apprised the meeting. CEO, Jammu Smart City Limited, Devansh Yadav informed that under Phase-1 (Part B), works related to end-to-end promenade flooring, landscaping, and electrical fixtures on the left bank and central island are progressing well.

He further divulged that the project has achieved 55% physical and 40% financial progress and is targeted for completion by next 2-3 months. The works include installation of decorative lighting at two promenade levels, plantation with drip and sprinkler irrigation systems, and paving using Kota stone and paver blocks.

The Chief Secretary also reviewed protection works being executed by UEED at multiple vulnerable locations, including Christian Colony, Gujjar Nagar, Prem Nagar, and Jogi Gate, along with retaining wall and nallah diversion works near Peer Kho. The total project cost for these works is ₹11.96 Cr and is currently under tendering.

Regarding the interception and diversion of major nallahs, it was informed that two major packages are under execution. In Package-1, covering the Gujjar Nagar to Tawi Bridge stretch, civil works have reached 92% completion while Package-2 on the right bank has achieved 85% completion, including RCC pipeline laying and construction of a 10 MLD equalisation tank. Some works were damaged during flash floods in August 2025, and restoration is currently underway, with revised timelines extending to March.

Emphasising timely completion, the Chief Secretary directed all executing agencies to accelerate the pace of work, maintain strict quality control, and adhere to project timelines, particularly in view of the upcoming flood season. He reiterated that the project will transform Jammu into a modern riverfront city, enhancing urban mobility, flood management, environmental sustainability, and economic potential.

Your voice can reach the world: At JK Monitor, we firmly believe that every well-researched idea has the power to inspire change beyond geographical boundaries. We are delighted to share an encouraging message from one of our esteemed contributors, Dr. Rakesh Verma (J&K Forest Services). “His article, ‘When Trees Become Rights-Bearing Citizens: A Lesson from Canada for India’s Ecological Future,’ published on JK Monitor, received appreciation from La Compagnie des Papillons Bleus, the French non-profit organisation that founded and promotes the Universal Declaration of Tree Rights.”.  Read the message here
In loving memory of Dr. Priya Ranjan: A mentor who treated me like family
A Profound Loss: JK Monitor Mourns the Passing of Founding Chairman Dr. Priya Ranjan

We at JK Monitor are profoundly saddened by the sudden demise of our Founding Chairman, Dr. Priya Ranjan.IN LOVING MEMORY Dr Priya Ranjan

A brilliant mind who studied at Netarhat Residential School and graduated in Electrical Engineering from IIT Kharagpur before earning his PhD from the University of Maryland, Dr. Ranjan chose to return to India and dedicate his life to teaching, research and social good.

His pioneering work in networked systems, AI, robotics and biomedical applications—especially computer-vision tools for early detection of cancer and heart disease—reflected his deep belief that advanced technology must serve humanity.

For more than 15 years at JK Monitor, he remained a loyal friend, mentor and collaborator, marked by rare humility, intellectual integrity and quiet generosity. His passing leaves a void that cannot be filled. Priya, you will be deeply missed. Your life continues to remind us that knowledge finds its highest purpose in the service of others.

— Team JK Monitor

       LOOK_HERE.jpg Esteemed readers, for your convenience, we have categorized our news publishing into following 👇