JAMMU: Minister for Jal Shkati, Javed Ahmad Rana, today informed the House that the Tawi River Front Project (Phase 1) shall be completed in April, 2025 with an allotted cost of Rs 143.00 crore. The Minister was replying to a question raised by Arvind Gupta in the Legislative Assembly. He informed that 96 percent and 94 percent physical progress has been achieved on the left bank and right bank of the river respectively.

Regarding the Tawi Barrage works, the Minister said that the works have been taken up with an estimated cost of Rs. 64.80 crore and Rs. 36.15 crore have been expended, so far. He said that 85 percent of the works of Tawi Barrage and Artificial Lake stand completed.  

The Minister said that in order to prevent the direct drain discharge into the Ranbir Canal, a detailed DPR for an amount of Rs 34.06 crore has been prepared for execution of 10 works.

Your voice can reach the world: At JK Monitor, we firmly believe that every well-researched idea has the power to inspire change beyond geographical boundaries. We are delighted to share an encouraging message from one of our esteemed contributors, Dr. Rakesh Verma (J&K Forest Services). “His article, ‘When Trees Become Rights-Bearing Citizens: A Lesson from Canada for India’s Ecological Future,’ published on JK Monitor, received appreciation from La Compagnie des Papillons Bleus, the French non-profit organisation that founded and promotes the Universal Declaration of Tree Rights.” Read the message here

       LOOK_HERE.jpg Esteemed readers, for your convenience, we have categorized our news publishing into following 👇